Construction contracts under the Civil Transactions Law

The definition of a construction (muqawala) contract, the obligations of the contractor and the employer, when payment falls due, lump-sum pricing and how the contract ends, with the texts of the Civil Transactions Law.

The construction contract (muqawala) is one of the most disputed contracts in the market: late delivery, disagreements over price, or defects in the work. The Civil Transactions Law regulates it in Articles 461 to 478.

Statutory texts below are our own English translation, provided for guidance. The official Arabic text prevails.

What is a construction contract?

Article 461 provides:

A muqawala is a contract under which the contractor undertakes to make a thing or perform work in return for a price, without being subordinate to the employer or acting as his representative.

The contractor's obligation may be to carry out the work with materials supplied by him or by the employer (Article 462).

The difference from an employment contract: the contractor is independent and does not work under the employer's direction. As for employment contracts, Article 479 provides that "employment contracts are governed by the legal provisions specific to them".

The contractor's obligations

Materials: under Article 463, if the contractor supplies the materials, he is responsible for their meeting the agreed conditions and specifications, or otherwise for their being fit for purpose according to custom. If the employer supplies them, the contractor must take care of them with the diligence of an ordinary person and return whatever remains.

Machinery and tools: Article 464 provides:

The contractor bears the cost of the machinery and tools required to complete the work, unless otherwise agreed.

Time and conditions: Article 465 provides:

The contractor shall complete the work in accordance with the terms of the contract and within the agreed period. If there are no terms or no period has been agreed, he shall complete it in accordance with recognized practice and within the reasonable period required by the nature of the work.

Breach by the contractor: Article 466 provides:

  1. If the contractor breaches the terms of the contract while the work is in progress, the employer may give him formal notice to comply with them and to correct the work within a reasonable period that he specifies. If that period expires without correction, the employer may entrust another contractor with completing or correcting the work at the first contractor's expense, in accordance with Article 167 of this Law, or may request rescission of the contract.
  2. The employer may request immediate rescission of the contract if the defect cannot be remedied, or if the contractor delays starting or completing the work to such an extent that he cannot be expected to finish it within the agreed period.

Loss of the work before delivery: under Article 467, if the work perishes or is damaged before delivery for a cause beyond the contractor's control, the contractor may not claim the price or his expenses, unless the employer was at that time in breach of his obligation to take delivery of the work. If the materials were supplied by the employer, he may not claim their value from the contractor, unless the contractor had been given formal notice for failing to deliver.

The employer's obligations

Taking delivery: under Article 468, the employer must promptly take delivery of the work once the contractor has completed it and placed it at his disposal. If he refuses without a legitimate reason, and the work perishes or is damaged in the contractor's hands without the contractor's transgression or negligence, the contractor is not liable for compensation.

When payment falls due: Article 469 provides:

  1. The employer shall pay the price upon taking delivery of the agreed work, unless otherwise agreed.
  2. If the work consists of several parts, or the price is set on a unit basis, the employer shall pay the contractor the part of the price corresponding to the work completed, after inspecting and accepting it, provided that the completed work is distinct or significant in relation to the work as a whole.

Unit-rate estimates: under Article 470, if it becomes clear during the work that the estimate must be exceeded substantially, the contractor must immediately inform the employer of the expected increase, failing which he loses his right to anything above the estimate. If the excess is grave, the employer may withdraw from the contract without delay, paying the contractor the value of the work completed.

Lump-sum price: Paragraphs (1) and (2) of Article 471 provide:

  1. If the construction contract is concluded on the basis of an agreed design for a lump-sum price, the contractor may not claim any increase in the price, even if the prices of materials used in the work, workers' wages or other costs rise.
  2. If the design is modified or added to, the contractor may not claim any increase in the price unless this is due to the employer's fault, or was done with his permission and he agreed with the contractor on the increase.

Paragraph (3) of the same Article makes an exception for general exceptional circumstances that were unforeseeable and cause the financial basis of the contract to collapse. In that case the court may restore the balance of the contract, including by extending the performance period, increasing or reducing the price, or rescinding the contract.

If no price was set: the contractor is entitled to the fair market price for the work, together with the value of the materials he supplied (Article 472).

Subcontracting

The contractor may assign all or part of the work to a subcontractor, unless this is prohibited by a provision, an agreement or the nature of the work, or the contractor's personal qualities were a material consideration. He remains liable to the employer (Article 473). The subcontractor may not claim from the employer anything owed to the contractor except through an assignment (Article 474).

When does a construction contract end?

  • On completion of the work: "A construction contract ends upon completion of the agreed work" (Article 475).
  • Rescission for a sudden excuse: Article 476 provides: "Either contracting party may request rescission of the construction contract if a sudden excuse relating to the performance of the contract arises for him, and he shall compensate the other party for the harm resulting from that rescission."
  • Inability of the contractor for a cause beyond his control: Article 477 provides: "If the contractor begins performance and then becomes unable to complete it for a cause beyond his control, he is entitled to the value of the work completed and to the expenses incurred on the unfinished work, to the extent of the benefit the employer derives from it." See force majeure.
  • Death of the contractor: the contract is dissolved if it was stipulated that the contractor would perform the work personally, or his personal qualities were a material consideration. Otherwise, the employer may request rescission if the heirs do not provide sufficient guarantees. The heirs are entitled to the value of the work completed and the expenses incurred, to the extent of the benefit the employer derives from them (Article 478).

Where is a construction claim filed?

If the construction contract is between two merchants and relates to their commercial business, or the claim is brought against a merchant in a dispute over a commercial contract where the original claim exceeds five hundred thousand riyals, the Commercial Court has jurisdiction (Article 16 of the Commercial Courts Law and Article 31 of its Implementing Regulations). Before filing, the defendant must be notified in writing at least fifteen days in advance (Article 19).

Note: claims concerning construction works contracts are not treated as small claims even if their value is less than one million riyals (Article 237 of the Implementing Regulations of the Commercial Courts Law). See commercial disputes.

Tips for drafting a construction contract

  • Define the scope of work, specifications and drawings precisely, and attach them to the contract.
  • Link payments to completion milestones that can be inspected and accepted (Article 469).
  • Regulate change orders in writing: who requests them, how they are priced, and their effect on the timeline (Article 471).
  • Set the performance period, the delay penalty and its maximum.
  • Regulate subcontracting: is it allowed, and with whose approval?
  • Add a force majeure clause; see Force majeure in civil contracts.
  • Specify the dispute resolution method: the courts or arbitration.

References

  • Civil Transactions Law issued by Royal Decree No. (M/191) dated 29/11/1444H: Articles 461–479.
  • Commercial Courts Law: Articles 16 and 19, and its Implementing Regulations: Articles 31 and 237.

This article is general information for awareness, not legal advice. Every case has its own details, so book a consultation to discuss your contract.