Force majeure in civil contracts

When is a debtor released from performance and compensation because of force majeure, and how does it affect the contract? A plain-language explanation of the Civil Transactions Law, with applications in sale, lease and construction contracts.

When an event beyond a contracting party's control prevents performance, many people ask: does my obligation fall away, and must I pay compensation? The Civil Transactions Law answers through its force majeure provisions, which most of its articles express as "a cause beyond his control".

Statutory texts below are our own English translation, provided for guidance. The official Arabic text prevails.

Force majeure in the text of the Law

The Law names force majeure expressly as an example of a cause beyond a person's control. Article 125 provides:

A person shall not be liable if it is proven that the harm arose from a cause beyond his control, such as force majeure, the fault of a third party or the fault of the injured party, unless otherwise agreed.

Effect on the contract: extinction of the obligation and automatic dissolution

Article 110 provides:

  1. In bilateral contracts, if performance of an obligation becomes impossible for a cause beyond the debtor's control, his obligation and the corresponding obligation are extinguished, and the contract is dissolved by operation of law.
  2. If the impossibility is partial, the obligation is extinguished only as to the impossible part and its counterpart. This rule also applies to temporary impossibility in time-based contracts. In both cases the creditor may request rescission of the contract, and the court may reject the request if the impossible portion is of little significance in relation to the obligation.

Article 294 provides:

The debtor's obligation is extinguished if he proves that performance has become impossible for him for a cause beyond his control, and the corresponding obligation, if any, is likewise extinguished.

What does this mean?

  • Total impossibility: both obligations are extinguished, and the contract is dissolved without the need for a court judgment.
  • Partial impossibility: only the impossible part and its counterpart are extinguished, and the creditor may request rescission of the whole contract.
  • Temporary impossibility in time-based contracts (such as leases and periodic supply contracts): treated like partial impossibility.
  • Burden of proof: the debtor must prove the impossibility and that it arose from a cause beyond his control.

What is the effect of dissolution?

Article 111 provides:

  1. Where a contract is rescinded or dissolved, the contracting parties are restored to the position they were in before contracting. If this is impossible, the court may award compensation.
  2. If the contract is a time-based contract, rescission or dissolution has no retroactive effect, and the court may award compensation where warranted.

Force majeure and compensation

The debtor is not ordered to pay compensation if he proves that non-performance or delay was due to a cause beyond his control:

  • Non-performance: Paragraph (3) of Article 170 provides: "Compensation under paragraphs (1) and (2) of this Article shall not be awarded if the debtor proves that the non-performance was due to a cause beyond his control."
  • Delay: Article 171 provides:

If the debtor delays performance of his obligation, he shall compensate the creditor for the harm he suffers because of the delay, unless he proves that the delay in performance was due to a cause beyond his control.

Can the parties agree otherwise?

Yes. Article 174 provides:

It may be agreed that the debtor shall bear the consequences of force majeure.

So if the contract states that the debtor bears the consequences of force majeure, he is not released from them. This is why the drafting of the force majeure clause matters.

Applications in specific contracts

Sale: Article 329 provides:

  1. If the sold item perishes before delivery for a cause beyond the control of either party or of a third party, the sale is dissolved and the buyer recovers the price.
  2. If only part of the sold item perishes, the sale is dissolved as to that part and the buyer recovers the corresponding part of the price. The buyer may request rescission of the sale as to the remainder and recover the full price.

Lease: Article 420 provides:

If the leased property perishes totally during the lease term, the contract is dissolved by operation of law.

Construction (muqawala): Article 477 provides:

If the contractor begins performance and then becomes unable to complete it for a cause beyond his control, he is entitled to the value of the work completed and to the expenses incurred on the unfinished work, to the extent of the benefit the employer derives from it.

See also Article 467 on the perishing of the work before delivery, in our article on construction contracts.

Note: force majeure is not the same as exceptional circumstances or a sudden excuse

Force majeure makes performance impossible. Exceptional circumstances (Article 97) make performance excessively burdensome while still possible, and a sudden excuse in construction contracts (Article 476) allows a party to request rescission subject to compensation. Each has its own conditions and rules.

Practical tips

  • Drafting the clause: specify in your contract which events count as force majeure, how and when notice must be given, the effect on deadlines and obligations, and who bears the consequences (Article 174).
  • Documentation: record the event and its direct effect on your obligation at the time it happens, because the burden of proof is on you.
  • Notice: notify the other party in writing as soon as the event occurs.
  • Distinguish: separate what makes performance impossible from what only makes it more costly, because the rules differ.

References

Civil Transactions Law issued by Royal Decree No. (M/191) dated 29/11/1444H: Articles 110, 111, 125, 170, 171, 174, 294, 329, 420, 467 and 477.


This article is general information for awareness, not legal advice. Every case has its own details, so book a consultation to discuss your contract.